Carpenter By The Numbers
- Building Square Footage: 68,056 ft2
- Number of Teaching Spaces: 50
The referendum projects began at Carpenter in the summer of 2025, featuring the addition of new all-inclusive playgrounds. The remaining renovations and upgrades are scheduled to be completed during the summer of 2026. These upgrades include significant improvements in health, safety, and security, as well as enhancements to mechanical infrastructure and classroom facilities.
Below is a list of what will be completed during the summer of 2026, and our plan to maintain these systems while addressing any items we could not fund with the referendum.
Health, Safety, and Security
-
Abate hazardous materials.
-
Replace room signage.
-
Replace classroom doors, frames, and hardware.
-
Replace select interior corridor (hallway) doors, frames, and hardware.
-
Replace fire alarm devices.
Mechanical and Infrastructure Improvements
- Replace ceiling tile.
- Replace flooring and carpet.
- Add a new generator.
- Replace lights in the LRC.
- Repaint the building as needed.
- Replace playground equipment and surfaces. (Completed in 2025.)
- Replace classroom sinks.
- Replace water fountains.
- Retrofit faucets with hands-free.
- Replace galvanized piping in the walls.
- Replace sinks in the restrooms.
- Replace urinals.
- Replace toilets.
Classroom Renovations
- Replace cabinets and cubbies.
- Replace countertops.
- Convert general classrooms to a special education suite for Healthy Opportunities for Positive Empowerment (H.O.P.E).
Following the support of our referendum, we are fulfilling our commitment to long-term fiscal responsibility by reevaluating our 30-year facility roadmap. We have partnered with McKinstry, a leading strategic facility planning partner, to perform independent, third-party engineering assessments of our building systems. This partnership provides the District with a live system for tracking asset health and remaining life, allowing us to stay ahead of repairs and protect the community's investment in our schools for decades to come.
-
Field Engineering
June 2026
McKinstry engineers begin a comprehensive physical assessment of all eight District schools to catalog every major building system (HVAC, electrical, plumbing, and roofing).
-
immediate tracking
Summer 2026
New equipment installed during recent construction projects is added to our 30-year roadmap to ensure we are tracking its health from day one.
-
Financial Modeling
Fall 2026
Field data is analyzed to determine the observed remaining life of our assets.
This phase involves building a customized financial dashboard to predict repair costs and prioritize work based on educational impact.
-
Plan Finalized
Fall 2026/Winter 2027
The Board of Education will review the final report and refined 30-year plan.
This data-driven roadmap will be used to guide all future capital budget decisions.
Once the McKinstry study is finished, we will add the projects that were not included in the referendum here.
Carpenter's Construction Budget
| Total construction budget | toTal Cost Via Bid |
|---|---|
| $4,212,764 | *$5,996,768 |
*For the purpose of this illustration, we have combined all the work being funded by the referendum and our Capital Fund 60. This amount also includes the playgrounds.