Long Term Capital Planning 2026-2055

This page provides the long-term capital improvement replacement schedule between 2026 and 2055. The dollar amounts are estimates based on industry averages in school districts and provided by our architects, mechanical engineers, and actual quotes obtained over time. The following assumptions are important to understand how the calculations are made: 

  1. School districts must pay prevailing wage.
  2. There is an annual escalation increase of 3%.
  3. Numbers do not include potential energy saving credits, grants, etc.
  4. Recommended replacement times are based on current age and the recommended life cycle per category
  5. A contingency of $150,000 is added per year.

The overall average to fund all projects would be $4,000,000 per year out of the district budget totaling $123,331,096.

Carpenter Elementary School Long Term Plan

Jefferson Early Childhood Center Long Term Plan

Emerson Middle School Long Term Plan

Field Elementary School Long Term Plan

Franklin Elementary School Long Term Plan

Roosevelt Elementary School Long Term Plan

Washington Elementary School Long Term Plan

Lincoln Middle School Long Term Plan

Together We Learn, Grow, Connect, & Care

At D64, our vision is that every child is empowered to discover their voice, reach their full potential, and make a positive impact on the world. Student growth, driven by rigorous curriculum and effective instruction, makes District 64 one of the best PreK-8 school districts in the state.

This site provides information using PDF, visit this link to download the Adobe Acrobat Reader DC software.